PROJECT INFORMATION

capacity

Summerfield is a four-hour 240MW / 960 MWh battery.

Location

Near Mannum in South Australia, approximately 20km from the Tungkillo switching station.

Size

222 battery containers over one hectare of land.

Benefits

Powering 70,000 or nearly 10% of South Australian homes every day. 

 
E-Storager Logo

In collaboration with Canadian Solar

We have selected Canadian Solar and its subsidiary e-STORAGE as our trusted construction partner for this project. e-STORAGE is a leader in designing, manufacturing, and integrating large-scale battery energy storage systems.

e-STORAGE will deliver its advanced SolBank 3.0 battery energy storage system, ensuring integration, commissioning, and long-term operational support. Leveraging its extensive global experience and top-tier technical capabilities, e-STORAGE is well positioned to unlock the full potential of battery storage, contributing to South Australia's renewable energy goals.

Supporting renewable energy

The Summerfield Battery will support South Australia’s clean energy ambitions by storing more affordable renewable energy when the sun is shining and the wind is blowing, and releasing it into the grid when it is needed most. 

The project will also allow South Australia to export more renewable energy to Victoria and New South Wales via the planned interconnector.

Delivering for South Australia

  • Further enabling South Australia’s rapid clean energy transition

  • Storing energy during low demand periods

  • Releasing energy during high demand periods 

  • Exporting renewable energy interstate 

  • Enabling more cheap large-scale wind and solar projects

  • Helping to avoid blackouts and the associated community impacts and costs

  • Maintaining grid stability 

  • Delivering more affordable and reliable power 

  • A portion of proceeds from the project go directly to local communities initiatives

sTAGE 01 Feasibility

Complete 2019

  • Site selection

  • Site engineering assessment

  • Environmental impact assessments

  • Early engagement with landowners

sTAGE 02 application & engagement

Complete 2020-2021

  • Project concept design

  • Initial community engagement

sTAGE 03 license & agreement

In progress 2022-2024

  • Obtain government licences and permits to build and operate the project

  • Grid connection and transmission studies

sTAGE 04 Construction & Community

from LATE 2024-2026

  • Build the project

  • Continue community engagement

  • System testing and commissioning

sTAGE 05 Operation

from 2027

  • Project operations

  • Regular maintenance